Provided, installed, and started up the control and electrical gear for the phase II addition to the ACWWA wastewater Treatment Plant. This plant uses the Zenon treatment and filtration system. This project utilized Allen Bradley PLCs and Iconics’ Wonderware man-machine interface.
| Engineer: | Browns Hill Engineering & Controls, LLC | ||
| General Contractor: | DCCI | ||
| Completion Date: | March 2001 |
Browns Hill Engineering & Controls has partnered with The Pagosa Area Water & Sanitation District to handle all the controls and system integration for a new building at the Hatcher Water Treatment Plant Facility. The facility will include the construction of two trains of rapid and coagulation tanks, membrane feeding pump, two separate microfiltration trains, chemical storage and feed facilities for sodium hydroxide, aluminum based coagulant, chloride dioxide, chlorine, and CIP cleaning chemicals and tankage, and all associated yard piping, site work, electrical/instrumentation and controls, and mechanical work.
Provided, programmed, and commissioned the electrical gear and control system for the expansion for the WWTP. This plant utilizes an Allen-Bradley PLC and Intellution software for the man-machine interface.
| Engineer: | McLaughlin Engineering | ||
| General Contractor: | Glacier Constructors | ||
| Completion Date: | October 2003 |
Provided, programmed, and commissioned the electrical gear and control system for the expansion for the WWTP. This plant utilizes an Allen-Bradley PLC and Intellution software for the man-machine interface.
| Engineer: | CDM | ||
| General Contractor: | Southwest Constructors | ||
| Completion Date: | January 2004 |
Provided, programmed and commissioned the electrical gear and controls for a new booster pumping station with 700 HP of pumping capacity.
| Engineer: | Muller Engineering | ||
| General Contractor: | Paramount Constructors | ||
| Completion Date: | March 2001 |
Provided, programmed, and installed the electrical gear and instrumentation and controls for the project. This project consists of a new water filter treatment plant.
| Engineer: | RTW | ||
| General Contractor: | Bosco Constructors | ||
| Completion Date: | November 2003 |